Auto Assign Mode

    Inspire Planner users are able to automatically assign project tasks to resources using Project Teams and roles (for more information, please see Auto Assign Tasks to Project Team Members using Roles). With the Auto Assign Mode feature, users can specify when the task assignment takes place - immediately, on demand, or when the task is ready to start.

    Please see Admin Guide - Auto Assign Mode for instructions on how to enable this feature in your Salesforce org.


     

    • Immediately - when Auto Assign Mode is set to this option, the task assignment occurs as soon as you create project team members and populate roles. The related Salesforce Tasks are created immediately. You will see the assigned resources' names in the Assigned To field.
       
    • On Demand - when Auto Assign Mode is set to this option, the task assignment occurs when you set "Execute Task Assignment" to TRUE. This means you can create project team members and populate roles, but the related Salesforce Tasks are only created when you set "Execute Task Assignment" to TRUE. You will not see the assigned resources' names in the Assigned To field until the task assignment is executed. When you are ready to assign the tasks, simply set "Execute Task Assignment" to TRUE. 

      When you set "Execute Task Assignment" to TRUE, Inspire Planner looks for project tasks where the role is populated and automatically assigns them to project team members with the same role. As soon as the process is done, it sets "Execute Task Assignment" back to FALSE. This means that if you add new project team members or edit project team members and roles, no further task assignment will occur until you set "Execute Task Assignment" to TRUE. This allows you to tell Inspire Planner when to create the related Salesforce Tasks. 

      Please Note:
      - Execute Task Assignment can only be set to TRUE if Auto Assign Mode is set to "On Demand".
      - Flows can be used to customize how this works. For more information or for a design consult, please reach out to your Customer Success or Onboarding Manager.
       
    • Ready to Start - when Auto Assign Mode is set to this option, the task assignment occurs when project task "Ready to Start" is TRUE. This means you can create project team members and populate roles, but the related Salesforce Tasks are only created when the project task "Ready to Start" is set to TRUE. You will not see the assigned resources' names in the Assigned To field until the task assignment is executed. For more information on "Ready to Start", please see Ready to Start.

      Please Note:
      "Ready to Start" defaults to TRUE for Project tasks without predecessors. This means that if Auto Assign Mode is set to "Ready to Start", all project tasks without predecessors are assigned immediately.
       
    • Blank - if no value is selected in Auto Assign Mode, then the task assignment occurs immediately (same as setting Auto Assign Mode to "Immediately").


     

    Task Assignments and Notifications

    When the project setting called "Send Task Notification" is TRUE on the project, a task notification email is sent to the assigned user as soon as the Salesforce Task is created.

    For contacts, they only receive task notification emails when both "Send Task Notification" on the project is TRUE, and the "Enable contact task assignment" setting is enabled in Inspire Planner Settings. For more information, please see Task Notifications and Reminders.

     

    The Auto Assign Mode determines when the task is assigned and the related Salesforce Task is created. This means that the assigned resource only receives the task notification email when the task assignment takes place.

     

     Auto Assign Mode
    Immediately (or Blank)On DemandReady to Start
    Assigned To cellPopulated immediately Populated only when you set "Execute Task Assignment" to TRUE"Populated only when the project task "Ready to Start" is TRUE
    Salesforce TaskCreated immediatelyCreated only when you set "Execute Task Assignment" to TRUE"Created only when the project task "Ready to Start" is TRUE
    Task Notification Email
    (If "Send Task Notification" is TRUE in Project Settings)
    Is sent as soon as the Salesforce Task is createdIs sent when the Salesforce Task is createdIs sent when the Salesforce Task is created
    Ready to Start Notification Email
    (If configured in your Salesforce org. For more information, please see Configuring Email Notifications for Ready to Start Tasks)
    Is sent when the project task "Ready to Start" is TRUEIs sent when the project task "Ready to Start" is TRUESince the task notification email is sent to the resource only when the Salesforce Task is created, which is when the project task is ready to start, we do not recommend setting up a Ready to Start notification email anymore.

     

     