Project Gantt - Adding Constraints to Your Project Schedule

    Last Modified On: November 5, 2026

     

    Overview

    Constraints define the scheduling limitations that a project task must operate within. They allow you to control when a task can start or finish, regardless of changes to the project schedule or its predecessor tasks.
     

    By default, a project task’s Start Date or Finish Date is determined by the project’s scheduling direction:

    • Forward-scheduled projects: Tasks are scheduled based on the project’s Start Date.
    • Backward-scheduled projects: Tasks are scheduled based on the project’s End Date.
       

    Tasks with predecessors are automatically rescheduled as soon as possible (ASAP) in forward-scheduled projects or as late as possible (ALAP) in backward-scheduled projects, based on the completion or scheduling of their predecessors.


    When the project Start Date or End Date is adjusted, or a predecessor task is rescheduled, the scheduling engine automatically recalculates the affected task dates.
     

    However, there may be situations where a task needs to start or finish by a specific date. For example, imagine a task scheduled for a technician to perform an onsite installation on a particular date. To ensure the installation can proceed as planned, the predecessor task (in this case, hardware delivery) must be completed by a specific date.
     

    You can apply a constraint, such as Finish No Later Than or Must Finish On, to the hardware delivery task to ensure it meets the required deadline.
     

    Once a constraint is applied, the scheduling engine respects the specified scheduling limitation when recalculating task dates. This prevents the task from being freely rescheduled based on changes to the project Start Date or End Date or the scheduling of its predecessors.

     

    One important distinction: Constraints do not necessarily prevent a task’s dates from changing altogether. Rather, they limit how the scheduling engine can adjust those dates based on the selected constraint.

     

     

    Adding Constraint Type & Constraint Date Columns to the Project Schedule

    By default, the Constraint and Constraint Date columns are hidden in the project schedule. To add them, simply right-click on any column heading, go to Columns and select both Constraint Type and Constraint Date.

     

     

    Constraint Types

    There are six (6) constraint types available for you to choose from. They are as follows:

     

    Hard Constraints

    A hard constraint means that the task has to start or finish on a particular date (constraint date) and cannot be rescheduled.

    • Must Start On - the task must start on a specific date (constraint date).
    • Must Finish On - the task must finish on a specific date (constraint date).

     

    Flexible Constraints

    A flexible constraint means that a task can be rescheduled as long as it does not violate the constraint date.

    • Start no earlier than - the task cannot start earlier than the constraint date.
    • Start no later than - the task cannot start later than the constraint date.
    • Finish no earlier than - the task cannot finish earlier than the constraint date.
    • Finish no later than - the task cannot finish later than the constraint date.

     

    When you add a constraint to a task, it will not be automatically rescheduled if the project's start or end date changes, or if its predecessor tasks are rescheduled.

     

    When you remove a constraint, the task is rescheduled as follows:

    • Forward-scheduled projects
      • Task has no predecessor - Task Start Date is rescheduled to the same date as project start date
      • Task has a predecessor - Task start/finish date is rescheduled as-soon-as-possible following its predecessor.
         
    • Backward-scheduled projects
      • Task has no predecessor - Task Finish Date is rescheduled to the same date as project end date
      • Task has a predecessor - Task start/finish date is rescheduled as-late-as-possible following its predecessor.

     

    Constraint Violation Messages

    As previously mentioned, when you add a constraint to a task, it will not be automatically rescheduled if the project's start or end date changes, or if its predecessor tasks are rescheduled. Instead, if the project start or end date changes, or if its predecessors are rescheduled wherein it's causing the task with a constraint to violate its constraint, you are prompted with a constraint violation message.

     

     

    • Deactivate dependency - this means that a previously defined relationship between tasks is no longer in effect. When you select this option, it will keep the dependency line connecting the task with its predecessor in the Gantt chart. However, the dependency line will display as a broken line to indicate that the previously defined relationship is no longer active. Any changes made to the predecessor task will no longer impact/reschedule the successor task.

      Example of a deactivated dependency between tasks in the Gantt chart:


       
    • Remove dependency - when you select this option, Inspire Planner eliminates/removes a previously established link between the task and its predecessor.
       
    • Remove constraint - when you select this option, Inspire Planner removes the task's constraint and the task is rescheduled according to the project start or end date (if it has no predecessor), or according to its predecessor task.
       
    • Cancel the change - will cancel the change you made to the schedule that is causing the task to violate its constraint.