Set Field-Level Security for Constraint & Constraint Date

    You will need to set the field-level security for both Constraint and Constraint Date to visible so that all Inspire Planner users are able to see and use these fields.

     

    1. Click the Gear icon at the top right corner and go to Setup.


       
    2. Go to Object Manager.


       
    3. Enter "Task" in the QuickFind box and click on Project Task.


       
    4. Go to Fields & Relationships.


       
    5. Enter "constraint" in the QuickFind box and click on Constraint Date.


       
    6. Click on Set Field-Level Security.


       
    7. Set it to "Visible" for all profiles and click on Save.


       
    8. Repeat the steps above for Constraint Type.

     

     