Don Wedd

    Task completion when task assigned to multiple resources

    If a task is assigned to 2 users, will the task be completed when the first one marks their Salesforce task "completed", or not until both mark it "completed"?


    2 years ago

    Replies

    Thai Nguyen

    Staff Contributor

    Hi Don, 

    Project Tasks are marked as Completed when ALL related Salesforce Tasks are set to Completed.

    Best,
    Thai

    5 months ago
    Answer
    Mark as Answer