Don Wedd

    Task completion when task assigned to multiple resources

    If a task is assigned to 2 users, will the task be completed when the first one marks their Salesforce task "completed", or not until both mark it "completed"?


    one year ago

    Replies

    Thai Nguyen

    Staff Contributor

    Hi Don, 

    Project Tasks are marked as Completed when ALL related Salesforce Tasks are set to Completed.

    Best,
    Thai

    one month ago
    Answer