Inspire Planner can display Start Week and Finish Week values for project tasks, helping users identify when tasks are scheduled to begin and end within the project timeline.
This article outlines the configuration steps administrators must complete to enable these fields and make them available to users in the project schedule.
You must be a Salesforce System Administrator to complete the steps outlined in this article as it requires access to Salesforce Setup and Administration.
The following Inspire Planner Standard Permission Sets already include access to the Start Week and Finish Week fields in the Project Task object.
If you are using custom permission sets, you must update them to grant users access to these fields.
Configure the Week Start Day setting in Inspire Planner to specify which day of the week is used as the starting point when calculating the Start Week and Finish Week values for project tasks. If no value is configured, Monday is used as the default.
Set the Week Start Day to specify which day of the week is used as the starting point when calculating the Start Week and Finish Week values for project tasks.
Enter the corresponding numeric value for your preferred start day:
Click Save to save your changes.Note:If no value is configured, Monday (2) is used as the default.
To make the Start Week and Finish Week fields available as columns in the Project Gantt, you must add both fields to the Inspire Planner Custom Fields field set on the Project Task object.