Last Modified On: May 6, 2026
See below for a definition of all Formula Fields in Inspire Planner and how they are calculated.
The percentage that the Project has slipped against the ((Actual Duration - Baseline Duration) / Baseline Duration). A negative value defines the project has completed ahead of schedule.
The planned duration of the project, calculated from the rolled-up Start Date and Finish Date values derived from related Project Task dates. This field represents the total number of working days or calendar days, depending on the Weekends Are Workdays setting.
Calculates the completed duration/work completed for a task based on:
the task duration
the duration unit (days, weeks, months, years)
the % complete (Done)
Checks whether the task’s current Status should be treated as a Completed status.
Determines a task’s status color/health indicator based on how many days overdue the task is (green, amber, red).
Returns On Time, At Risk, or Late based on Duration, % Complete, Finish Date, and Days Remaining.On Time when:
At Risk when:
Late when:
For more information, please see Project Task Health Indicator.
This field displays a different image/icon depending on the value in the Task Health field.
Determines the Assignment Completion Rule for a task. The formula checks:
Is the task set to override the project-level rule?
If yes - then use the opposite of the project rule
If no - then inherit the project rule
If project rule is blank - then default to "All to Complete"
Calculates the planned/budgeted cost for an assignment or task, depending on a system configuration setting.
Categorizes task due date into time buckets. Instead of showing the raw date only, it returns labels like:
Today
Tomorrow
This Week
Next Month
Past Dates
Calculates the allocated planned effort for a resource assignment (% allocation x planned effort).
Determines the owner/assignment type of a Salesforce task and returns one of these values - user, contact, or queue.
Categorizes task start date into time buckets. Instead of showing the raw date only, it returns labels like:
Calculates the total daily resource capacity/hours available per day (number of resources x working hours per day).
Displays a priority/risk indicator icon based on the numeric value of priority level. Returns a green, amber, or red icon.