Inspire Planner Formula Fields

    Last Modified On: May 6, 2026

     

    See below for a definition of all Formula Fields in Inspire Planner and how they are calculated.

     

    Project 

    Field NameDefinition / How It's Calculated
    % OverdueThe percentage the Project is overdue (Days Overdue / Project Duration)
    % CompleteTotal Project % Complete based on the Project Tasks contained within the Project. For more information on how this field is calculated, please see Project - How % Complete is Calculated.
    % Slippage

    The percentage that the Project has slipped against the ((Actual Duration - Baseline Duration) / Baseline Duration). A negative value defines the project has completed ahead of schedule.

    Actual DurationThe duration of the Project based on actual execution dates. Calculated from Project Actual Start Date and Project Actual Finish Date. This field reflects the number of calendar days between those dates and updates automatically when either date changes.
    Baseline DurationDefines the number of days the project will take based on baseline Start and Finish dates.
    Cost Performance Index (CPI)Measures the value of work completed against the Actual Cost. A CPI Value < 1 indicates costs where higher than budgeted while a CPI > 1 indicates that costs were less than budgeted (Earned Value / Actual Cost)
    Cost VarianceThe difference between Earned Value and Actual Cost. (Earned Value - Actual Cost)
    Cost Variance % The percentage of variance between Earned Value and Actual Cost ((Earned Value - Actual Cost) / Actual Cost)
    Days Overdue (Project)The number of days that the Project is overdue. If there is a Baseline Finish Date, it is calculated by taking the difference between the Actual Finish Date and the Baseline Finish Date. If there is no Baseline Finish Date, then it takes the difference between the current date and the Actual Finish Date.
    Days to CompletionThe number of days remaining until Project completion (Actual Finish Date - Today)
    Duration

    The planned duration of the project, calculated from the rolled-up Start Date and Finish Date values derived from related Project Task dates. This field represents the total number of working days or calendar days, depending on the Weekends Are Workdays setting.

    Earned EffortEffort earned based on % Complete of the Project (Total Planned Effort * % Complete)
    Earned ValueBudget earned to date based on the Project % Complete. (Budgeted Cost * % Complete)
    Effort VarianceThe difference between the Total Planned Effort and Total Actual Effort for the Project (Total Planned Effort - Total Actual Effort)
    Effort Variance %The percentage of variance between Total Planned Effort and Total Actual Effort ((Total Planned Effort - Total Actual Effort) / Total Planned Effort)*100
    Estimated at Completion (EAC)A forecast of how much the total project will cost. (Budgeted Cost / CPI)
    Finish VarianceThe difference between the baseline Finish date and the actual Finish Date (Actual Finish Date - Baseline Finish Date)
    Planned ValueDefined as the amount the Project should have earned based on current date against Project Duration and Budgeted Cost. If current date is less than Project Start Date, then Planned Value is at $0. (Project Duration - ((Project Finish Date - TODAY) + 1) / Project Duration) * Budgeted Cost)

    *This is not a formula field on the project, but is populated by the Inspire Planner Nightly Job. It is included in this help article to provide information on how this field is calculated.
    Owner NameDisplays the Project Owner Name
    Remaining BudgetThe difference between Budgeted Cost and Actual Cost (Budgeted Cost - Actual Cost)
    Remaining EffortThe difference between Planned Effort and Actual Effort (Total Planned Effort - Total Actual Effort)
    SlippageThe number of days the Project has slipped against the baseline. Negative value means that the Project completed ahead of schedule (Actual Duration - Baseline Duration)
    Start VarianceThe difference between baseline Start Date and actual Start Date (Start Date - Baseline Start Date)

     

     

    Project Task 

    Field NameDefinition / How It's Calculated
    % OverdueThe percentage the Project Task is overdue (Days Overdue / Project Duration)
    % SlippageThe percentage the Project Task has slipped against the original baseline ((Actual Duration - Baseline Duration) / Baseline Duration)
    Days OverdueThe number of days that the Task is overdue. It takes the difference between the current date and the Task Finish Date.
    DurationThe duration of the Task based on the Start and Finish Dates
    Duration Complete

    Calculates the completed duration/work completed for a task based on:

    • the task duration

    • the duration unit (days, weeks, months, years)

    • the % complete (Done)

    Finish Date OnlyTask Finish Date 
    Finish Variance 1The difference between the baseline 1 Finish date and the Finish Date (Finish Date - Baseline 1 Finish Date)
    Finish Variance 2The difference between the baseline 2 Finish date and the Finish Date (Finish Date - Baseline 2 Finish Date)
    Finish Variance 3The difference between the baseline 3 Finish date and the Finish Date (Finish Date - Baseline 3 Finish Date)
    Finish Variance 4The difference between the baseline 4 Finish date and the Finish Date (Finish Date - Baseline 4 Finish Date)
    Finish Variance 5The difference between the baseline 5 Finish date and the Finish Date (Finish Date - Baseline 5 Finish Date)
    Remaining BudgetThe difference between Project Task Budgeted Cost and Actual Cost (Budgeted Cost - Actual Cost)
    Remaining EffortThe difference between Planned Effort and Actual Effort (Total Planned Effort - Total Actual Effort)
    Start Date OnlyTask Start Date
    Start Variance 1The difference between baseline 1 Start Date and Start Date (Start Date - Baseline 1 Start Date)
    Start Variance 2The difference between baseline 2 Start Date and Start Date (Start Date - Baseline 2 Start Date)
    Start Variance 3The difference between baseline 3 Start Date and Start Date (Start Date - Baseline 3 Start Date)
    Start Variance 4The difference between baseline 4 Start Date and Start Date (Start Date - Baseline 4 Start Date)
    Start Variance 5The difference between baseline 5 Start Date and Start Date (Start Date - Baseline 5 Start Date)
    SlippageThe number of days the Project has slipped against the baseline. Negative value means that the Project completed ahead of schedule (Actual Duration - Baseline Duration)
    sysCompleted

    Checks whether the task’s current Status should be treated as a Completed status.

    sysCompletedStatusesReferences completed status values from custom settings.
    sysParentTaskLookupIdId of the Parent Task record. Used for validation.
    sysTaskLED

    Determines a task’s status color/health indicator based on how many days overdue the task is (green, amber, red).

    Task Earned ValueBudget earned to date based on the Project Task % Complete. (Budgeted Cost * % Complete)
    Task Health

    Returns On Time, At Risk, or Late based on Duration, % Complete, Finish Date, and Days Remaining.

    On Time when:

    • Required fields are blank (duration, % complete, finish date)
    • Task is completed and finished on or before the planned finish date
    • Task is not complete, but there is still enough time left
    • Task is incomplete, planned finish date has not passed, and business/calendar day comparison passes (based on whether weekends are working days) 

    At Risk when:

    • Task is not complete and planned finish date has not passed and remaining effort is more than the remaining available time.

    Late when:

    • Task is completed, but finished after the planned finish date (Actual Finish Date is later than planned Finish Date)
    • Task is not complete and the planned finish date has already passed

    For more information, please see Project Task Health Indicator.

    Task Health Indicator

    This field displays a different image/icon depending on the value in the Task Health field.

    Task Completion Rule

    Determines the Assignment Completion Rule for a task. The formula checks:

    Is the task set to override the project-level rule?

    If yes - then use the opposite of the project rule

    If no - then inherit the project rule

    If project rule is blank - then default to "All to Complete"

    Task Planned ValueDefined as the amount the Task should have earned based on current date against Task Duration and Budgeted Cost. If current date is less than Task Start Date, then Planned Value is at $0. (Task Duration - ((Task Finish Date - TODAY) + 1) / Task Duration) * Budgeted Cost)

     

    Activity 

    Field NameDefinition / How It's Calculated
    Budgeted Cost

    Calculates the planned/budgeted cost for an assignment or task, depending on a system configuration setting.

    • If use effort to calculate cost setting is TRUE, then budgeted cost = planned effort x billable rate.
    • If use effort to calculate cost setting is FALSE, then use Project Task budgeted cost.
    DueDateGroup

    Categorizes task due date into time buckets. Instead of showing the raw date only, it returns labels like:

    • Today

    • Tomorrow

    • This Week

    • Next Month

    • Past Dates

    Parent TaskReference to parent task name related to Inspire Task.
    Planned Effort

    Calculates the allocated planned effort for a resource assignment (% allocation x planned effort).

    Project NameName of project related to Inspire Task.
    Ready to StartIdentifies if all Predecessors have been met and task is ready to be started. Referenced from related Project Task.
    Resource Type

    Determines the owner/assignment type of a Salesforce task and returns one of these values - user, contact, or queue.

    StartDateGroup

    Categorizes task start date into time buckets. Instead of showing the raw date only, it returns labels like:

    • Today

    • Tomorrow

    • This Week

    • Next Month

    • Past Dates

    sysContactTaskEmailReference to Inspire Planner custom setting which defines if email notification should be sent to Contact for new task assignment.
    sysTemplateTaskDetermines if Task is related to Project Template. This is used as filter criteria for Resource Allocation calculation.
    Task HealthReferenced from related Inspire Planner Project Task. Defines current health of Task based on Duration, % Complete, Finish Date, and Days Remaining. This field displays a different image/icon depending on the value in the Task Health field.

     

    Resource Profile

    Field NameDefinition / How It's Calculated
    Resource NameDisplays resource name regardless if User or Contact
    Total Hours per Day

    Calculates the total daily resource capacity/hours available per day (number of resources x working hours per day).


    Risks and Issues

    Field NameDefinition / How It's Calculated
    Priority LevelCalculates a risk score by multiplying impact level x probability level.
    Priority Indicator

    Displays a priority/risk indicator icon based on the numeric value of priority level. Returns a green, amber, or red icon.

    • Green when priority level < 6
    • Amber when priority level > 6 and < 19
    • Red when priority level >19


    Time Entry

    Field NameDefinition / How It's Calculated
    Billable AmountCalculates the total billable amount based on Billable Rate and Time Spent.
    Labor CostCalculates the total Labor Cost based on Cost Rate and Time Spent.
    Resource NameName of resource time entry belongs to. Determines between user vs contact.
    sysFlagForCalcIdentifies if the record should be included in next rollup execution.

     

    Timesheet

    Field NameDefinition / How It's Calculated
    Approver NameDisplays the name of the timesheet approver.
    Hours VarianceThe difference between Target Hours and Total Hours logged for Timesheet.

    Tags

    Administration

    « Previous ArticleNext Article »