Ready to Start Indicator

    Last Modified On: June 26, 2025
     

    The Ready-to-Start indicator helps you quickly identify which project tasks are ready to begin. A task is marked as Ready-to-Start when all of its dependencies (such as predecessor tasks) have been completed.

     

    This visual cue makes it easier for project managers and team members to focus on tasks that are actionable now—helping to keep the project on track and avoid delays.

     

    Inspire Planner automatically marks a project task as “Ready to Start” when all of its predecessor tasks have been completed.

     

    Predecessor TypeReady to Start is TRUE when
    Finish to StartPredecessor Task is Complete (or equivalent) and there is no lag
    Start to StartPredecessor Task is In Progress, Completed (or equivalent) and there is no lag
    Finish to FinishAlways TRUE unless there is lag
    Start to FinishPredecessor Task is In Progress, Completed (or equivalent) and there is no lag

     

    When you adjust the status of a predecessor task according to the chart above, there is a trigger in Inspire Planner that will automatically set "Ready to Start" to TRUE on both the Project Task and the related Salesforce Task.

     

    The Ready to Start trigger will also fire if any of the following are changed:

    • Task Status
    • Task Type 
    • Predecessors
    • Predecessor Task Start Date or Finish Date
    • Predecessor Task Status

     

    Please note the following:

    • Even if the predecessor task’s finish date has passed or the successor task’s start date has arrived, the successor task will not be marked as “Ready to Start” unless the predecessor’s status meets the required conditions outlined in the table above.
       
    • If there is no lag between tasks, the successor task will be marked as “Ready to Start” as soon as the predecessor meets the required status conditions—regardless of whether the successor’s start date has been reached.
       

    • When there is lag time between dependent tasks, Inspire Planner automatically creates a Sync Queue record to update the schedule at the appropriate time.

      • For Start-to-Start dependencies, the Sync Queue is scheduled to run at the beginning of the day on the task’s Start Date.

      • For Finish-to-Start dependencies, the Sync Queue is scheduled to run at the end of the day before the task’s Start Date.
         

    • ​​​The “Ready to Start” checkbox in the Project UI does not automatically update when the status of predecessor tasks changes. To see the latest status, you’ll need to manually refresh the interface. For the most accurate view, we recommend checking the “Ready to Start” indicator directly on the related Salesforce Task, as this is where assigned resources typically manage their work.

     

    Viewing "Ready to Start" Indicator in the Project Interface


    To see the Ready to Start column in the Project UI, simply right-click on any column heading. Then, go to Columns and check the box for "Ready to Start".

     

     

    Viewing "Ready to Start" Indicator in Salesforce Tasks

    As mentioned at the beginning of this help article, when a the status of a task is changed to "Completed", "In Progress", or equivalent, Inspire Planner automatically sets its successor task "Ready to Start" to TRUE for both the Project Task and related Salesforce Task. This section will walk you through how to add the "Ready to Start" checkbox on your Salesforce Tasks.

     

    1. Click on the Gear Icon at the top right corner and go to Setup.


       
    2. Go to Object Manager.


       
    3. Enter "Task" in the Quick Find box at the top right corner and click on Task.


       
    4. Go to Page Layouts.


       
    5. Locate the Task Page Layout you are using then click on the drop down arrow on the right and click on Edit.


       
    6. Drag the "Ready to Start" field from the list of available fields at the top, to your desired area on the page. When finished, click on Save.


       

    If you still cannot see the "Ready to Start" field in Project Task and/or Salesforce Task even after you've added it to the page layouts, you likely need to set the field-level security to visible. Please see Set Field-Level Security for Ready to Start Field

     

    If you would like to receive email notifications when your tasks are ready to be started, you will need to configure an email alert workflow. Please see Configuring Email Notifications for Ready-to-Start Tasks.


    Tags

    Project Task List

    « Previous ArticleNext Article »